October 27th
The chairs are in place, bring on the snow!
September 29th
Construction nears completion, cables have been strung and the chairs are next!
August 17th
Doppelmayr was onsite to fly towers for the new Alpine Meadows chairlift.
July 21st
Doppelmayr was onsite to fly concrete for the new Alpine Meadows chairlift. The Bell 214 machine was long-lining a bucket for several hours. The top terminal and 3 tower foundations were poured. All the foundation holes have been dug and now forming is ongoing. All the towers, line equipment and chairs have been delivered and are ready for installation.